6 x 3 Mezzanine Installation Process
Our 6 x 3 mezzanine is designed for quick, efficient installation with minimal disruption to your operations. Using prefabricated modular components, we complete most of the work off-site and assemble on-site in just 1–2 days.
Day 1:
Stand and secure columns to the ground
Day 2:
Deliver mezzanine floor modules and crane them into position
Fit-outs such as offices, storage rooms, cool rooms, or amenities are additional works. A separate program will be provided for these installations.